Desk Report: Overseas West Sector A, Lahore Smart City
Infrastructure work continues across Overseas West Sector A. A recent ground assessment outlines the current development status, street by street, including utility preparation, paving, and footpath construction.
Street Number 1
Earthwork and soil filling have been completed along the road corridor. Watering and ground preparation are finished, clearing the way for paving. Tuff tile installation is scheduled to start on the prepared surface. Utility poles stand on one side of the street, but light fixtures have not yet been installed. On the opposite side, the pedestrian footpath remains pending, with more poles and fixtures planned for later phases.
Street Number 2
Paving has advanced substantially. Roughly 80 percent of the tuff tiles on the developed portion were previously laid. On an unfinished patch, materials have arrived, earth has been spread, and final watering and compaction are still needed before tiles can be laid. Where paving is done, street light poles and active fixtures are in place, and walkways on both sides are mostly paved. The street is not complete over its full planned length; about half of the corridor up to specific mapped plots is paved, while the remaining stretch farther down shows no active work.
Lane Number 16
This lane runs behind the plots facing the Ring Road inside Sector A. Sand and sub-base material have been laid, and watering and compaction are nearly complete. Footpath paving is underway, with crews handling tile delivery and installation. Beyond Street Number 3 along Lane 16, tuff tiles cover most of the road surface, with only minor edge detailing and finishing left.
Street Number 3
Paving is advanced here. Nearly 90 percent of the road surface has installed tuff tiles. A small remaining segment must be finished to connect smoothly with nearby paths. Workers are placing pavers by hand on the compacted base, bringing this section near structural completion.
Street Number 4 and Street Number 5
Street Number 4 has an almost complete footpath framework on both sides, with only small gaps left for final tiling. Pavers are stacked nearby to finish those sections. The paved road portion has completed tuff tiles on both sides. Still, only about 40 to 45 percent of the total street alignment is developed, leaving plots along the next section without road infrastructure. No street lighting poles have been installed yet.
Street Number 5 mirrors Street Number 4. The main road surface in the developed section is paved, and its connection to Lane Number 16 needs only final edge alignment. Part of the pedestrian footpath still requires finishing, and light poles have not been erected. Work on Street 5 covers roughly 40 to 45 percent of its mapped length, with no visible construction on the remaining part.
Street Number 6 and Street Number 7
Work shifts to foundational earthworks on Street Number 6. Initial ground leveling is done, and concrete kerb stones mark the footpath boundaries on both sides. Tuff tile installation for the carriageway and walkways has not started and remains pending until paving teams move forward from earlier streets.
On Street Number 7, heavy earthmoving equipment has finished basic ground leveling. Curbs are aligned on one side to outline the walkway, while the other side still needs curbing. Underground sewerage installation is partially incomplete along this corridor. Full surface development and tile paving will follow once foundational utilities are complete.
Street Number 8 and Street Number 9
Street Number 8 runs beside a designated neighborhood park area. Basic leveling across the road alignment is complete, and curb stones outline the green space perimeter. Footpath completion and road paving remain pending.
Street Number 9 is at the same stage. The surface is leveled, a curved curb borders the open park quadrant, but roadway surfacing, footpaths on the opposite side, and electrical pole installation have not yet occurred.
Street Number 10, Street Number 11, and Beyond
Street Number 10 focuses on deep utility infrastructure. About 80 to 90 percent of the underground sewerage network is installed, while road leveling, curbing, and surfacing are on hold pending final utility sign-off.
Street Number 11 consists of raw earth mounds and initial excavation areas where digging began earlier. No resurfacing, leveling, or structural paving has advanced recently. Past Street Number 11 toward the outer perimeter plots and areas facing the Ring Road next to the executive sector, the ground remains raw and undeveloped, unchanged from previous survey periods.